The U.S. Army told an appeals court that it will detonate a stockpile of lead azide in Iowa, even if its permit from the U.S. Environmental Protection Agency is on hold.
In a court filing on Saturday, Nov. 21, an attorney from the U.S. Department of Justice notified the court that the Army would, if necessary, invoke emergency exclusions to the EPA’s regulatory requirements to detonate the 68 barrels of lead azide at the Iowa Army Ammunition Plant in Middletown no later than Tuesday, Nov. 24.
In an update Sunday evening, the Army said the detonation would take place on Wednesday, Nov. 25.
The Army has warned the blast will send up a plume of toxic lead dust that could travel 100 miles or more from the blast site. Lead is a neurotoxin that poses particular hazards to the elderly, very young children and pregnant women, and there is no safe level of exposure.
The Army’s permit was challenged in the U.S. Eighth Circuit Court of Appeals by the Iowa Environmental Council and the Sierra Club’s Iowa chapter. The groups argued the EPA skipped necessary steps in issuing the permit for the detonation, which was originally scheduled for Friday, Nov. 20.
The court put an administrative stay on the permit so that it could review the groups’ emergency motion.
In its filing Saturday, the federal government said there is “an immediate risk” that the lead will explode as temperatures drop below 30 degrees in the upcoming days. The National Weather Service forecast calls for highs in Middletown in the low 40s and overnight lows reaching the low 20s.
The bunkers housing the lead are more susceptible to temperature swings now because the blast doors were removed in preparation for the detonation and cannot be replaced, the filing said.
In a follow-up filing Sunday, the government asked the court to deny the plaintiffs’ motion and lift the stay on the EPA permit, which includes provisions requiring testing and cleanup of contaminated areas after the blast. The Army intends to follow those mitigation requirements, whether or not the permit is formally reinstated, it says.
The Sunday filing argues that federal officials have already considered the alternatives suggested by the environmental groups, such as chemically neutralizing the explosives in place, and rejected them. The explosive material is so degraded that even opening the lids of the 55-gallon plastic barrels poses an unacceptable risk of setting off an explosion, the filing says.
“The choice therefore is not between a detonation and no detonation,” it argues. “It is between a planned detonation (timed for favorable weather, preceded by public notice, and followed by monitoring and cleanup) and an unplanned explosion that could come at any moment, with no warning and no safeguards.”